Clayton
County
Justice
Complex
Jonesboro, Georgia
A major feature of this county detention
facility, housing 2000 inmates, was
the use of six-sided precast cell modules
that were fully upfitted.
The
new $110 million Clayton County Justice Complex in Jonesboro, Georgia is
a mammoth facility comprising a county detention facility, new courthouse
and renovation of existing structures. The precast concrete portion of
the facility is the new detention facility
The detention
facility consists of four octagonal housing pods containing a total of
768 inmate cells, a dormitory housing unit containing four occupancy areas,
and a corridor structure connecting the pods and dormitory to the new courthouse.
In addition to the precast cell modules, flat panels, double tees, bents,
and hollow-core slabs were used.
The owner's
initial motivation for choosing precast concrete was a rash of escapes
taking place from an existing detention facility of masonry
construction. Inmates were literally breaking through the walls. In addition,
the county detention facility population has been rapidly growing and had
found itself increasingly unable to properly house inmates and detainees.
The new precast detention facility structure incorporates contemporary
detention design concepts together with the high strength of precast and
prestressed concrete and state-of-the-art security equipment.
The owner
discovered another advantage of precast concrete after planning had begun.
Limitations in construction time and the budget were quickly encountered.
The use of precast concrete allowed the job to be completed up to a year
earlier than estimates for other building systems. In addition to saving
construction interest and project overhead costs, precast concrete looked
attractively priced as a building system compared to other high security
systems such as filled masonry.
The architect,
program manager, and general contractor formed a design-build team. The
engineers and representatives from the precast concrete producer (Tindall
Corporation) performed a number of value engineering analyses. These efforts
optimized the design, accelerated completion, and further reduced project
cost.
The structural
design consisted of vertical flat panels with opposed haunches to accept
double tee floors and roof deck members. Certain floor areas were incorporated
in hollowcore slabs with a structure of columns and inverted tee beams.
All floors were covered with a nominal 2-in. (51-mm) topping slab. The
roof was untopped.
The two-level
corridor presented a unique design challenge. The lower level provides
secure passage for prisoners between booking, housing, and the court. The
upper level provides secure visitor access in each housing unit. The structural
design included haunched panels, hollow-core slabs and structural bents.
The precast
modules incorporate a number of innovative features. These features were
the result of Tindall’s long experience with the modular cell product.
The insulated
back wall is independently flatcast on a bed. It consists of a 2 in. (51-mm)
outer wythe and 2 in. (51 mm) of isocyanurate foam insulation. After curing,
the casting bed is rotated 90 degrees and then incorporated in the module
form. The module provides the inner (structural) wythe in this non-composite
construction. By this method, the back wall is of architectural quality
because it is not vertically cast and can incorporate an architectural
concrete mix design. In addition, the insulation coverage is 100 percent
and insulation placement is certain because the insulation is not subject
to movement due to casting hydraulics or vibration. This feature is invisible
to the uninformed observer.
A more
obvious innovative feature is that the modules are six-sided with an integral
floor. Until recently, all cell modules had been five-sided with the bottom
open. In this older system, the lower level unit sits on a slab on grade
and the mezzanine level unit uses the roof of the lower level module as
a floor.
The six-sided
modules were built with a prestressed floor slab. The mezzanine level units
have a cantilevered balcony. The advantages to the owner for this system
are faster erection, precise door fit, and an improved interior finish
because there is no dry-pack grout joint at the floor. The contractor and
program manager also benefited from the faster erection. The six-sided
module sits on strip footings. Thus, the modules were the first trade on
the job. This further reduced project costs and offered coordination advantages
to the contractor.
Tindall
provided modules with the cell painted and fully upfitted with furniture,
ceiling light, and the toilet. This saved a great deal of time and money
and has become a commonly requested standard in today's detention construction
programs.
The modules also were provided
with a fully upfitted chase containing all plumbing, HVAC ductwork, and
electrical lines. These MEP systems were fully tested to code requirements
at the precast producer's plant. This saved both time and money compared
to site fabrication of the chase. This goes well beyond the commonly accepted
standard of performance.
The last
notable feature of precast construction on this job was the close coordination
between the module manufacturer and the mechanical and plumbing trades.
This allowed these trades to shop build most of their scope that connects
to the modules. The result was a substantial improvement in time and a
savings in project cost.
Tindall
Corporation fabricated the cell modules, double tees, and flat panels at
their plant in Conley, Georgia. They were shipped by tractor-trailer [a
distance of about 20 miles (32 km)] to the project site. Tindall was also
responsible for the erection of the cell modules and other precast components.
Coreslab Structures fabricated the hollow-core slabs at their plant in
Jonesboro, close to the project site.
Erection
of the precast concrete components began on March 15 and was completed
on October 27. This completion date was one day ahead of the original schedule,
despite the fact that the number of precast pieces increased by about 20
percent due to value engineering improvements. However, this re-engineering
provided the savings in time the owner was looking for. Now, the other
trades could begin work immediately and in full force.
The total
cost of the entire facility was about $110 million with the precast concrete
work amounting to approximately $11 million.
The facility
received its first inmate in October 2000; about 21 months after site work
began. This is a very rapid completion target for a facility of almost
2000 beds. In addition, the job was completed under budget.
The justice
facility is now operating with total satisfaction. In retrospect, the owner's
objectives of high security, rapid construction and low cost were met by
the precast concrete design.
CREDITS
Contact us